Construction Update 8-16-2016

Here is the latest on construction project.  The building inspector has approved the building for occupancy and we are working to take care of few minor things in preparation for Day 1.  Parts of the outside areas around the school are officially construction zones - requiring hard hats - and are off limits to the students and the general public for safety reasons.


Here is Door D-1, sidewalk is ready along with ramp to mobile classrooms M1 - M4.  Both sides are fenced in for safety purposes.


Here is Door C-1, also ready to go.  The area across the bus loop is a construction zone and is off-limits to the staff, students, and general public due to safety.  A parent asked me the other day if the hillside will be be cleared and ready for sledding in the winter.  A very interesting question - maybe not for this year, but we'll see.


The stairwell in the commons is not quite complete - waiting on the railings, risers, and treads to be installed.  Should be ready soon.  We have walled off the area to keep everyone safe.


Here is the lower commons with the temporary wall in place.  The new carpet has been installed and tables will be ready for students tomorrow.  Our Art teachers plan to hang some student artwork on the walls to spruce things up a bit.





Friday, August 12, 2016

Construction Update 8-12-2016

A few updates and photos of the school construction project. 


The existing commons is nearly ready and will be open on Wednesday. Additional seating will be available upstairs. 


The sidewalks and ramp outside door D-2. The classroom addition is to the right and the ramp to the mobile classrooms to the left. 


Sidewalks and ramp outside door C-2 is nearly finished as well.  The brick is going on classroom addition to the left; the new classrooms will be opened summer. 



Both sides of the commons addition are shown here; scheduled to be finished in March.


The new stairwell is nearing completion and will be ready soon. Treads, risers and railing to be installed. 


The brick is nearly complete on the physical education room and outdoor accessible restrooms. 


New and more powerful network nodes have been installed. More opportunities for blended learning using CANVAS and other tools. 

Wednesday, August 3, 2016

Construction Update 8-3-2016

Here's a few photos from the work site. 

New lights and ceiling grids being installed, new carpet will be installed next week.

Frame for the new stairwell in the commons.


View of the commons addition. Here you can see the footers of the new outer wall of the commons. This will almost double our seating space. 

The view from the door by Room 105. A new sidewalk will be poured soon and the new curb of the bus loop can be seen. 

A view of the new bus loop curbs, paving should started this week.

The floors of the classroom addition have been poured and interior walls will go up soon.

Thursday, July 28, 2016

Internship Opportunity with Governor Bevin

Good Afternoon,
 
The Office of Governor Matt Bevin is now accepting applications for our Fall Internship Program. As part of the program you will be exposed to the inner workings of state government and the Governor’s Office. We are seeking motivated individuals who are eager to learn and to better the entire Commonwealth of Kentucky. If you are interested in applying, you can find our online application here ->
http://governor.ky.gov/office/Pages/internships.aspx
 
The internships are unpaid, however we are able to work with your institution to ensure that you earn college credit for your work. If you have any questions please do not hesitate to reach out. The application deadline is August 12th at 5:00 pm.
 
 
Ben Goldey
Staff Assistant/Internship Program Coordinator
Office of Governor Matt Bevin
502-564-2611 ext. 343
Ben.goldey@ky.gov

Friday, July 22, 2016

Construction Update 7-22-2016

Here's a quick rundown of the construction project on the Ryle campus.

Outside of the lower commons. The windows and the sidewalks have been removed. The foundation of the new commons area is next. 

We will have the original commons space back the beginning of this school. The addition is expected to be finished sometime mid-year.


The exit outside Room 105, you can see the foundation and the walls of the classroom addition starting to go up. 


The classroom addition view from the second floor. Here you can see part of layout of the hallway and classrooms. 



These two pictures show where the hallways will continue forward into the new classroom addition. The estimated completion date of the classroom addition will be the 2017-18 school year. 


New ventilation ducts and lighting going up in the lower commons. 


This new stairwell in the commons will help the flow of foot traffic throughout the day and especially at lunch. 

Enjoy the rest of your summer!



Friday, June 17, 2016

Construction Update 6-17-2016

The view from the lower commons doors - showing the new drainage and where new sidewalks will be installed. 


These two shots show the area in which the new classroom addition will be built. 



In the background is the new path for the bus loop around the school.